Production schedule

12/11/15       
Al  Member

This subject probably has been discussed before. I am looking for suggestions on a production schedule. We are a 3-4 man shop. We produce 1 product and most commonly 3-4 different sizes. There are random orders of 16 different sizes also.
There is also 12 different steps from start to finish. The steps range from 20 parts per hour to 45 parts per hour.

12/12/15       #2: Production schedule ...
Lock Step

What have you tried so far, and what are you trying to achieve?

12/13/15       #3: Production schedule ...
Prasad Velaga

Website: http://optisol.biz

For production scheduling, people adopt various methods which include whiteboards, heijunka, kanban, CONWIP,
quick response manufacturing, Excel applications, drum-buffer-rope method of TOC, MS Project (scheduling software), finite capacity scheduling (enabled by software), etc. Some people may even make simple mental calculations for scheduling using their experience, intuition and commonsense. Each one of these methods is indeed effective in some cases but their relative merit varies with the situation.

I understand that:

1). Your job shop receives orders for different sizes and different quantities of a product probably with some uncertainty
2). Processing of any order involves 12 steps
3). Cycle time varies with processing step

I assume that a worker can perform more than one step but one at a time. I do not know whether:

1). All 12 steps are to be done in the same sequence for every order or the sequence may vary with order or some of the steps can run in parallel if required resources are available
2). Workers have different skill sets
3). Some steps need both machine and worker
4). Some steps require more than one worker simultaneously
5). Some machines are to be shared for different steps of production.
6). Material moves from one step to another either piece by piece or in terms of a single batch or a few small transfer batches
7). Two or more orders progress on shop floor simultaneously.

All these issues have an impact on production schedule. I wonder how you are able to (a) Quote a rational lead time for a new order given the existing workload and requirements and availability of meager resources and (b) Fix a right start time for the order. You may lose the order itself if you quote a long lead time. On the other hand, you and your workers may have a serious problem if you quote a lead time shorter than achievable. If you start an order too early, its production lead time may be longer and clutter the shop without any gain in the completion time due to the presence of earlier orders. On the other hand, if you start an order relatively later, you may miss its due date and lose some throughput.

Sometimes, resources may be unexpectedly unavailable due to various reasons. Changing order priorities or expediting an order can cause a major effect on delivery times of orders. Even though job shops are small in size and revenue, their production management is not easy in general. But, perpetual firefighting will hide the intensity of the problem.

I usually propose software-based finite capacity scheduling which provides prediction of workflow and bottlenecks, determines order lead times and right start times for orders and enables what-if analysis and capacity planning. Some job shop people feel it is too rigorous for them.

12/13/15       #4: Production schedule ...
Zach

Website: http://deasmillwork.com

I fully agree with prasad. We are in the process from changing from an excel based manual schedule to shedulize which prasad developed. It is going well and will be much better as well as very scaleable. If you are a four man shop it would be easy to implement and let it grow with your shop.

12/13/15       #5: Production schedule ...
Tim Schultz

Prasad,

I have a question about your question number 2) Workers have different skills.

How does your optimization software take into account differing process times associated with differing skill sets? How long something takes to make sometimes depends on who is performing the task.

Sometimes the task is performed incorrectly and needs to be redone. How does your optimization rebalance when this occurs?

In the case of sequential processes involving more than one person what is the mechanism to update your coworker that we are now ready for his input/involvement.

What is the actual mechanism for implementing this optimization? Is this implementation electronic or is it more akin to a Gantt chart printed out on paper?

Is it theoretical optimization or does it actually drive the shop? Do you need someone carrying a clipboard to update status or is this done at the level of individual worker?

12/13/15       #6: Production schedule ...
Prasad Velaga

Hi Tim,

Thanks for asking very relevant and right questions. Here is my response.

Our model handles the efficiency level / speed of workers to account for worker-dependent process times. It also considers preference levels for workers for any given skill. It allows a worker to have multiple skills with varying preference levels.

If some task requires more time from a worker than the estimate for any reason, let the worker continue until it is completed and select the next task in his task list that is generated as part of his schedule. We will update the schedule later as part of regular schedule revision. It is much easier to handle unexpected changes of moderate size by asking resources to implement task sequence rather than his schedule with specific start and finish times of tasks. The task sequence will absorb a lot of variation. If a task in the sequence (for a worker) is not ready at the required right time, then the worker can proceed with the following tasks in the sequence until this task is ready.

The actual mechanism for implementing this optimization is based on rigorous, finite capacity scheduling logic (my pet subject) and implemented on computer with the help of software.

You asked, "Is it theoretical optimization or does it actually drive the shop? Do you need someone carrying a clipboard to update status or is this done at the level of individual worker?".

Many real job shops have been regularly using our scheduling software, which is based on rigorous, scientific logic. As a past academician and researcher, I am happy that I could bring such rigorous, scientific scheduling logic to even small shop floors in real world.

Somebody in the shop (preferably scheduler) has to update the progress of each ongoing project (job) in our software whenever the schedule is to be revised.

12/13/15       #7: Production schedule ...
Tim Schultz


So does finite capacity scheduling create a system where work orders are not released until capacity is available to perform the task?

Would this work to help keep work in process at a minimum? Anything 2nd priority projects sitting around your shop that are half done competes for resources (carts - floorspace etc) that could be brought to bear on 1st priority tasks.

12/13/15       #8: Production schedule ...
Tim Schultz

There are also the unmeasurable (but nonetheless real) extra management costs associated with building something before it is needed.

Passing out tasks when they need to happen is hard enough without having to keep track of the things that didn't need to happen. Just keeping track of what has been done and what remains to be done is complex. Quite often you have to spend dollars to mop up the negative effects of over production. You certainly commit space to it and this space could instead hold a new work station or minimize transport costs navigating station to station.

The time and resources spent on these misfires could be better spent with Prasad's program. You're going to spend it anyway, you might as well get something for it.

12/13/15       #9: Production schedule ...
Al  Member

Great Input!!! Thank you

12/14/15       #10: Production schedule ...
Prasad Velaga

Hi Tim,

Your question:
So does finite capacity scheduling create a system where work orders are not released until capacity is available to perform the task?

Work orders will be released at right times so that they neither sit on shop floor for long time waiting for bottleneck resources nor they unnecessarily get delayed leaving a risk for late delivery, throughput reduction and resource underutilization. I am giving a link below for illustration.

Your question:
Would this work to help keep work in process at a minimum?

The given link should answer this question affirmatively. The number of horizonal lines that intersect a vertical line representing a time point on either diagram represent the number of jobs in process at that time point.

The yellow color in the second diagram on the web page represents controlled waiting times of jobs before bottlenecks.

Lean Production in Job Shops

12/14/15       #11: Production schedule ...
Larry

Seems like being "Lean" means eliminating unnecessary things. Start by defining the processes required. Make a flow chart for each product. Entry & exit points for processes/components. Where will a buffer be justified? Can sorting be done @ the off loading point from a machine, rather than a separate operation? When is another job started? When the current job is finishing the first operation or when the buffer is nearly empty. How do I tell when there is a problem in the flow? A buffer is either full or empty.
If that is the case you adjust resources, move labor. A properly designed system will make it obvious to employees when they need to shift. No management input required other than training.
Systems for handling small parts can work by just having tables between operations. No walking, no pushing carts.
Bigger systems can use roller conveyors & transfer cars.
The ideal system will allow visual control with little management and no computer inputs. Feeding a computer information that is not fully automated is a waste. Is the customer willing to pay for it?
Scheduling the supply of work is based on tracking production times and is based only on the limiting process.
Visual management is simple if the system has been designed correctly. You won't waste time counting, putting info into a computer. Computers are useful for the operations that take place before manufacturing.
Gantt charts are useful for setting up the manufacturing system. By analyzing flow charts you may be able to determine where product modifications will improve efficiency. KISS!


Post a Response
  • Notify me of responses to this thread
  • Subscribe to email updates on this Forum
  • To receive email notification of additions to this forum thread,
    enter your name and email address, and then click the
    "Keep Me Posted" button below.

    Please Note: If you have posted a message or response,
    do not submit this request ... you are already signed up
    to receive notification!

    Your Name:
    E-Mail Address:
    Enter the correct numbers into the field below:
     

    Date of your Birth:



    Return to top of page

    Buy & Sell Exchanges | Forums | Galleries | Site Map

    FORUM GUIDELINES: Please review the guidelines below before posting at WOODWEB's Interactive Message Boards (return to top)

  • WOODWEB is a professional industrial woodworking site. Hobbyist and homeowner woodworking questions are inappropriate.
  • Messages should be kept reasonably short and on topic, relating to the focus of the forum. Responses should relate to the original question.
  • A valid email return address must be included with each message.
  • Advertising is inappropriate. The only exceptions are the Classified Ads Exchange, Machinery Exchange, Lumber Exchange, and Job Opportunities and Services Exchange. When posting listings in these areas, review the posting instructions carefully.
  • Subject lines may be edited for length and clarity.
  • "Cross posting" is not permitted. Choose the best forum for your question, and post your question at one forum only.
  • Messages requesting private responses will be removed - Forums are designed to provide information and assistance for all of our visitors. Private response requests are appropriate at WOODWEB's Exchanges and Job Opportunities and Services.
  • Messages that accuse businesses or individuals of alleged negative actions or behavior are inappropriate since WOODWEB is unable to verify or substantiate the claims.
  • Posts with the intent of soliciting answers to surveys are not appropriate. Contact WOODWEB for more information on initiating a survey.
  • Excessive forum participation by an individual upsets the balance of a healthy forum atmosphere. Individuals who excessively post responses containing marginal content will be considered repeat forum abusers.
  • Responses that initiate or support inappropriate and off-topic discussion of general politics detract from the professional woodworking focus of WOODWEB, and will be removed.
  • Participants are encouraged to use their real name when posting. Intentionally using another persons name is prohibited, and posts of this nature will be removed at WOODWEB's discretion.
  • Comments, questions, or criticisms regarding Forum policies should be directed to WOODWEB's Systems Administrator
    (return to top).

    Carefully review your message before clicking on the "Send Message" button - you will not be able to revise the message once it has been sent.

    You will be notified of responses to the message(s) you posted via email. Be sure to enter your email address correctly.

    WOODWEB's forums are a highly regarded resource for professional woodworkers. Messages and responses that are crafted in a professional and civil manner strengthen this resource. Messages that do not reflect a professional tone reduce the value of our forums.

    Messages are inappropriate when their content: is deemed libelous in nature or is based on rumor, fails to meet basic standards of decorum, contains blatant advertising or inappropriate emphasis on self promotion (return to top).

    Libel:   Posts which defame an individual or organization, or employ a tone which can be viewed as malicious in nature. Words, pictures, or cartoons which expose a person or organization to public hatred, shame, disgrace, or ridicule, or induce an ill opinion of a person or organization, are libelous.

    Improper Decorum:   Posts which are profane, inciting, disrespectful or uncivil in tone, or maliciously worded. This also includes the venting of unsubstantiated opinions. Such messages do little to illuminate a given topic, and often have the opposite effect. Constructive criticism is acceptable (return to top).

    Advertising:   The purpose of WOODWEB Forums is to provide answers, not an advertising venue. Companies participating in a Forum discussion should provide specific answers to posted questions. WOODWEB suggests that businesses include an appropriately crafted signature in order to identify their company. A well meaning post that seems to be on-topic but contains a product reference may do your business more harm than good in the Forum environment. Forum users may perceive your references to specific products as unsolicited advertising (spam) and consciously avoid your web site or services. A well-crafted signature is an appropriate way to advertise your services that will not offend potential customers. Signatures should be limited to 4-6 lines, and may contain information that identifies the type of business you're in, your URL and email address (return to top).

    Repeated Forum Abuse: Forum participants who repeatedly fail to follow WOODWEB's Forum Guidelines may encounter difficulty when attempting to post messages.

    There are often situations when the original message asks for opinions: "What is the best widget for my type of shop?". To a certain extent, the person posting the message is responsible for including specific questions within the message. An open ended question (like the one above) invites responses that may read as sales pitches. WOODWEB suggests that companies responding to such a question provide detailed and substantive replies rather than responses that read as a one-sided product promotion. It has been WOODWEB's experience that substantive responses are held in higher regard by our readers (return to top).

    The staff of WOODWEB assume no responsibility for the accuracy, content, or outcome of any posting transmitted at WOODWEB's Message Boards. Participants should undertake the use of machinery, materials and methods discussed at WOODWEB's Message Boards after considerate evaluation, and at their own risk. WOODWEB reserves the right to delete any messages it deems inappropriate. (return to top)


  • Forum Posting Help
    Your Name The name you enter in this field will be the name that appears with your post or response (return to form).
    Your Website Personal or business website links must point to the author's website. Inappropriate links will be removed without notice, and at WOODWEB's sole discretion. WOODWEB reserves the right to delete any messages with links it deems inappropriate. (return to form)
    E-Mail Address Your e-mail address will not be publicly viewable. Forum participants will be able to contact you using a contact link (included with your post) that is substituted for your actual address. You must include a valid email address in this field. (return to form)
    Subject Subject may be edited for length and clarity. Subject lines should provide an indication of the content of your post. (return to form)
    Thread Related Link and Image Guidelines Thread Related Links posted at WOODWEB's Forums and Exchanges should point to locations that provide supporting information for the topic being discussed in the current message thread. The purpose of WOODWEB Forums is to provide answers, not to serve as an advertising venue. A Thread Related Link that directs visitors to an area with inappropriate content will be removed. WOODWEB reserves the right to delete any messages with links or images it deems inappropriate. (return to form)
    Thread Related File Uploads Thread Related Files posted at WOODWEB's Forums and Exchanges should provide supporting information for the topic being discussed in the current message thread. Video Files: acceptable video formats are: .MOV .AVI .WMV .MPEG .MPG .MP4 (Image Upload Tips)   If you encounter any difficulty when uploading video files, E-mail WOODWEB for assistance. The purpose of WOODWEB Forums is to provide answers, not to serve as an advertising venue. A Thread Related File that contains inappropriate content will be removed, and uploaded files that are not directly related to the message thread will be removed. WOODWEB reserves the right to delete any messages with links, files, or images it deems inappropriate. (return to form)