Today's
Sponsors:


AXYZ International

B.H. Davis Company

Bailey's Inc.

Baker Products

Barn Door Lumber

BC Wood Specialties Group

Beaver Tools

Benz Incorporated

Best Cabinets

Better Vacuum Cups

Biesse America

Biewer Lumber

Black Bros. Co.

Brown Wood Products Co.

Brunner Hildebrand Lumber Dry Kiln Co.

Byrd Tool

C.R. Onsrud

Cab Parts

Cabinet Door Service Co.

Cabinet Pro

CabinetCRUNCHER Cutlist & 3D Cabinet Design Software

Cabinetmakers Association

CabinetNow.com

CADCode

Cag Lumber

Cantek America

Carolina Machinery Sales

Carter Products

Casadei Busellato

Cascade Metal Designs LLC

Casewood

Castle

Catskill Timber Industries

Cefla North America

2Sand.com

3M Corporation

A O M Spray Equipment

Abrasive Resource

Accu-Router, Inc.

AceCo Precision Wood Tooling

Advanced Architectural Grilles

Air Handling Systems

Airtight Clamps

Alan McIlvain Company

Algoma Lumber Co.

All Star Adhesives

Alliance Knife Grinding & Moulder Service

Alliance Millsoft

Allied Machinery Inc.

AllRout

Amana Tool

American Fabric Filter Co.

American Institute of Building Design

American National Woodworking Knife

American Rotary Converters

Anchor Hardwoods of the Carolinas

Antique Beams and Boards

Antique Building Materials

Anver Corporation

Apollo Sprayers Inc.

ArtCam

ATEMAG

Auton Motorized Systems

AWFS




Estimating Long-Schedule Jobs

      Tips on projecting costs and covering yourself for changing conditions when getting involved in multi-year projects. November 4, 2007

Question
How do you handle a bid job that will be done over the course of several years? This job is a huge church with 3 phases of construction over 4 years, and that schedule can be thrown out the window probably. How do you handle pricing a job that won't be done for 4 years? Inflation alone will wreak havoc on margins 4 years old. Any thoughts?

Forum Responses
(Business and Management Forum)
From contributor G:
I'm surprised they're not making you bid per phase. That's the way an airport is that I'm working in now. I too have been thinking about this a lot lately, because even if it's 1 year out, it's too far. I would consider writing a stipulation in your contract about the materials. Something like you will absorb up to 3% increase in material costs, but the rest you are entitled to be compensated for, as you purchase material. I'm not sure how to address anything else that would change, but at least you'd be covered on the materials.



From contributor J:
I have done a lot of these type jobs. The furthest out has been 3 years with a contract of 9+ million. When we bid these type of jobs, we get the suppliers to confirm their prices for the duration of the job. At first they were hesitant, but after a bit of discussion they are happy to do this for us if they know they will receive the order. We bid it out just like a general and give them the bid results along with a purchase order. As far as labor goes, it is pretty easy to figure out. Wages and benefits go up between 3% to 5% per year. We are union, so we can pretty much depend on that type of raise.

The real important part to all of this is to keep the original schedule handy. When they start to fall behind, it will impact your labor with the new wages. When you put in a change order, this is very important and should be put into the contract on your behalf.



Would you like to add information to this article?
Interested in writing or submitting an article?
Have a question about this article?


Have you reviewed the related Knowledge Base areas below?
  • KnowledgeBase: Knowledge Base

  • KnowledgeBase: Business

  • KnowledgeBase: Business: Estimating/Accounting/Profitability




    Would you like to add information to this article? ... Click Here

    If you have a question regarding a Knowledge Base article, your best chance at uncovering an answer is to search the entire Knowledge Base for related articles or to post your question at the appropriate WOODWEB Forum. Before posting your message, be sure to
    review our Forum Guidelines.

    Questions entered in the Knowledge Base Article comment form will not generate responses! A list of WOODWEB Forums can be found at WOODWEB's Site Map.

    When you post your question at the Forum, be sure to include references to the Knowledge Base article that inspired your question. The more information you provide with your question, the better your chances are of receiving responses.

    Return to beginning of article.



    Refer a Friend || Read This Important Information || Site Map || Privacy Policy || Site User Agreement

    Letters, questions or comments? E-Mail us and let us know what you think. Be sure to review our Frequently Asked Questions page.

    Contact us to discuss advertising or to report problems with this site.

    To report a problem, send an e-mail to our Webmaster

    Copyright © 1996-2012 - WOODWEB ® Inc.
    All rights reserved. No part of this publication may be reproduced in any manner without permission of the Editor.
    Review WOODWEB's Copyright Policy.

    The editors, writers, and staff at WOODWEB try to promote safe practices. What is safe for one woodworker under certain conditions may not be safe for others in different circumstances. Readers should undertake the use of materials and methods discussed at WOODWEB after considerate evaluation, and at their own risk.

    WOODWEB, Inc.
    335 Bedell Road
    Montrose, PA 18801

    Contact WOODWEB













  •   Home » Knowledge Base » Knowledge Base Article